PROGRESS CONTINUES AT VICTORY PLACE

With beautiful weather and reliable crews, local Nebraska veterans get even closer to move-in day at Victory Place. Current work consists of rough-in framing. A 30-meter crane is currently onsite setting steel. The second-level framing will begin around June 7, and the roof is scheduled to be installed at the end of June. Then the MEP phase of the rough-in begins. The 26-unit apartment complex is on schedule to be completed in October 2016. Crews are busy!